Notice of Request for Proposals
Project #186-J-07-1 –
Peter R. Brown Construction, Inc. (CGC-061419), the Construction Manager for the St. Petersburg College Annex 2 Epicenter Project #186-J-07-1 hereby solicits sealed proposals for the referenced project in accordance with the proposal documents to include but not limited to the following:
The Scope of Work for this project includes but is not limited to the following:
A Build out of a 41,055 sq. ft. building shell for a new office, storage facility and related site work is included. The building has been gutted out. The interior of the building includes casework, new doors, frames and hardware. The scope will include painting of new partitions and soffits, acoustical ceilings, VCT, carpet, porcelain tile, projector screens, projector mounts, window treatment and accessories. The mechanical scope consists of a new chilled water system. New plumbing and fixtures are included. A fire sprinkler system will be added throughout the building. The electrical and low voltage systems include fire alarm, communications/data, and CATV. Exterior canopies will be added at exterior doors. The site will require sitework, landscape irrigation and sod.
A pre-proposal meeting for the trades referenced above will be held at 10:00 a.m. (Local Time), May 2, 2008, and a pre-proposal meeting for H.V.A.C and Electric will be held at 10:00 a.m. (Local time), February 26, 2008
Both will be held at the following location:
Project Site
Deadline for receipt of HVAC & Electric Proposal Packages has been set for 2:00 p.m., March 11, 2008
Deadline for receipt of All Other Proposal Packages has been set for 2:00 p.m., May 15, 2008.
Only proposals received on or before the time and date listed will be considered. All proposals received after 2:00 p.m., of the day specified above, will be returned unopened.
All interested subcontractors must be pre-qualified or have completed the pre-qualification process within the last year. Please contact the following person to obtain information or documents about the pre-qualification requirements for this project:
Joe Ostrowski, Senior Estimator
Phone: (727)535-6407 – Fax: (727)529-8485
One set of plans and specifications will be supplied to all pre-qualified trade contractors at no cost. Drawings for HVAC and Electric will be available February 5, 2008. Drawings for all other trades will be available prior to May 2, 2008 Preproposal Meeting Trade contractors are responsible for the cost of shipping. Additional sets may be purchased directly from the copy center. Copy center information will be distributed with the Proposal Packages.
No verbal instruction or directives will be accepted regarding this project during the proposal period. All instructions or directives must be clarified through written Addenda or Supplements. All questions regarding the work should be directed to the Construction Manager, in writing by HVAC & Electric by March 3, 2008 and all other trades by May 7, 2008. The Owner and Architect will not accept calls regarding this project.