5B-57.011: Biomass Plantings
PURPOSE AND EFFECT: The purpose of this amendment is to require that a new application for a Biomass Permit be submitted if the original permitted acreage is increased by more than 5%. It also requires permission of the landowner for the life of the biomass planting and allows a fallow area of more than 25 feet to serve as a containment mechanism.
SUMMARY: To clarify some of the requirements for containment and to require an additional application and permit if the original planting size is to be significantly increased.
SUMMARY OF STATEMENT OF ESTIMATED REGULATORY COSTS: No Statement of Estimated Regulatory Cost was prepared.
Any person who wishes to provide information regarding a statement of estimated regulatory costs, or provide a proposal for a lower cost regulatory alternative must do so in writing within 21 days of this notice.
SPECIFIC AUTHORITY: 570.07(13), (23) FS.
LAW IMPLEMENTED: 581.031(4), (5), (6), 581.083, 581.091 FS.
IF REQUESTED WITHIN 21 DAYS OF THE DATE OF THIS NOTICE, A HEARING WILL BE SCHEDULED AND ANNOUNCED IN FAW.
THE PERSON TO BE CONTACTED REGARDING THE PROPOSED RULE IS: Connie Riherd, Assistant Director, Division of Plant Industry, Department of Agriculture and Consumer Services, P. O. Box 147100, Gainesville, FL 32614-7100
THE FULL TEXT OF THE PROPOSED RULE IS:
5B-57.011 Biomass Plantings.
(1) Biomass Permit Requirements. It shall be unlawful to establish a biomass planting greater in size than two contiguous acres except under a biomass permit (Biomass Planting Permit, DACS-08382, revised 07/06) issued by the department for this purpose and is incorporated herein by reference. An application for new biomass permit will be required if the planting (contiguous or noncontiguous) will exceed five percent (5%) of the acreage of the orignal permit. No biomass permit shall be issued for any planting of plants on the state noxious weed list or the federal noxious weed list. No biomass permit shall be issued unless the applicant is the owner of the property or has written permission from the property owner to utilize the land for biomass plantings for the duration of the life of the permit. Applications for biomass permits shall be made on Biomass Planting Permit Application, DACS-08381, revised 08/06, and submitted to the Division of Plant Industry,
(a) A system of traps or filters shall be required to prevent plants or plant parts from spreading through ditches, natural waterways or other drainage. A fallow area in excess of 25 feet may be considered as a trap.
(b) Measures will be required to prevent spread by seed.
(c) A fallow area, wide enough to prevent plant spread into adjacent areas, shall be required. The fallow area may be used singularly or in combination with a berm will be on both sides of a berm surrounding the biomass planting.
(d) Any equipment used on the site must be cleaned of all plant debris before being moved from the property.
(e) Wildfire protection measures will be required to mitigate fire risk and damages to surrounding areas.
(f) A compliance agreement (Compliance Agreement, Biomass, DACS-08383, revised 07/06) containing any additional requirements needed to prevent plant spread shall be signed and will be an addendum to the permit for this purpose and is incorporated herein by reference. Copies of Compliance Agreement, Biomass, DACS-08383, revised 07/06, may be obtained from the Division of Plant Industry, Bureau of Plant and Apiary Inspection, P. O. Box 147100, Gainesville, FL 32614-7100. Failure to abide by the permit stipulations or the compliance agreement is considered to be a violation of these rules.
(2) Bonds or Certificates of Deposit. Each permit holder shall maintain for each separate growing location a bond or a certificate of deposit in an amount of not less than 150 percent of the estimated cost of removing and destroying the plants as described in Section 581.083(4), F.S. The bond or certificate of deposit may not exceed $5,000 per acre except as allowed by statute.
(3) Abandoned Biomass Plantings. It shall be unlawful for any person to abandon a biomass planting. It is the responsibility of the property owner or permit holder to completely destroy the planting prior to vacating the property or stopping commercial production. If the department determines that the permit holder is no longer maintaining or cultivating the plants subject to the special permit and has not removed and destroyed the plants authorized by the special permit or has exceeded the conditions of the biomass permit, the department shall take action to initiate the removal of the plants through the issuance of an immediate final order and execution of the bond or certificate of deposit as described in Section 581.083(4), F.S.
(4) Exemptions. A biomass permit is not required for plants produced for purposes of agriculture as defined in Section 570.02(1), F.S., or if the department in consultation with the
(a) Any plant that is produced for purposes of human food consumption.
(b) Any plant that is commonly grown for commercial feed, feedstuff or forage for livestock.
(c) Pinus spp.
Specific Authority 570.07(13), (23) FS. Law Implemented 581.031(4), (5), (6), 581.083, 581.091 FS. History–New 10-1-06, Amended________.