Notice of Proposed Rule

ADMINISTRATION COMMISSION
Rule No.: RULE TITLE
28-20.130: Work Program Administration
28-20.140: Comprehensive Plan
PURPOSE AND EFFECT: Proposal to adopt revised rules for Monroe County Work Program Administration and Comprehensive Plan to implement the Section 380.0552(4), Florida Statutes, annual reporting requirement to the Administration Commission describing the progress of Monroe County in accomplishing the remaining tasks under the Work Program as set forth in Rule 28-20.110, F.A.C, that are necessary prior to the removal of the Florida Keys Area of Critical State Concern designation.
SUMMARY: The proposed rules for the Monroe County Comprehensive Plan identify the individual Work Program tasks set forth in Rule 28-20.110, F.A.C., and the completion dates of the Work Program tasks necessary for consideration by the Administration Commission prior to Removal of the Area of Critical State Concern Designation. As required by Section 380.0552(4), Florida Statutes, the Work Program tasks specified in Administration Commission rules must be reported annually. The protection of the natural environment of the Florida Keys, and the identification of and progress in accomplishing the tasks under Work Program (as set out in Rule 28-20.110, F.A.C.) is reported to the Department of Community Affairs for the preparation of a written annual report to the Administration Commission. The Work Program tasks include the continued implementation of the Wastewater Master Plan and the construction of wastewater treatment and collection facilities; the continued implementation of the Florida Keys Carrying Capacity Study; the identification and completion of stormwater projects; and the analysis of hurricane evacuation issues in the Florida Keys.
SUMMARY OF STATEMENT OF ESTIMATED REGULATORY COSTS: A Statement of Estimated Regulatory Costs has been prepared.
Any person who wishes to provide information regarding a statement of estimated regulatory costs, or provide a proposal for a lower cost regulatory alternative must do so in writing within 21 days of this notice.
SPECIFIC AUTHORITY: 380.0552(9), 380.05(22) FS.
LAW IMPLEMENTED: 380.0552 FS.
IF REQUESTED WITHIN 21 DAYS OF THE DATE OF THIS NOTICE, A HEARING WILL BE HELD AT THE DATE,TIME AND PLACE SHOWN BELOW(IF NOT REQUESTED, THIS HEARING WILL NOT BE HELD):
DATE AND TIME: January 10, 2011, 10:00 a.m.
PLACE: Department of Community Affairs, 2555 Shumard Oak Boulevard, Room 305, Tallahassee, Florida 32399-2100
A SECOND POST LEGISLATIVE RATIFICATION HEARING WILL BE HELD AT THE DATE, TIME AND PLACE SHOWN BELOW.
DATE AND TIME: May 17, 2011, 9:00 a.m.
PLACE: Cabinet Meeting Room, Room LL03, The Capitol, Tallahassee, Florida
Pursuant to the provisions of the Americans with Disabilities Act, any person requiring special accommodations to participate in this workshop/meeting is asked to advise the agency at least 7 days before the workshop/meeting by contacting: Barbara Powell, Planning Analyst, Department of Community Affairs, 2555 Shumard Oak Boulevard, Tallahassee, Florida 32399-2100, telephone (850)922-1782. If you are hearing or speech impaired, please contact the agency using the Florida Relay Service, 1(800)955-8771 (TDD) or 1(800)955-8770 (Voice).
THE PERSON TO BE CONTACTED REGARDING THE PROPOSED RULE IS: Barbara Powell, Planning Analyst, Department of Community Affairs, 2555 Shumard Oak Boulevard, Tallahassee, Florida 32399-2100, Telephone (850)922-1782

THE FULL TEXT OF THE PROPOSED RULE IS:

28-20.130 Work Program Administration.

(1) Pursuant to Section 380.0552(4)(b), the Department of Community Affairs shall submit a written annual report to the Administration Commission on, November 30, 2011 and each year thereafter, until such time as the designation is removed, describing the progress of the Florida Keys Area toward accomplishing remaining tasks under the work program (as set out in Rules 28-20.110 and 28-20.140, F.A.C.), the fulfillment of the legislative intent and providing a recommendation as to whether progress toward accomplishing the tasks of the work program has been achieved.

(2) The Department of Community Affairs shall recommend to the Administration Commission the removal of designation when the removal of designation criteria of Section 380.0552(4), F.S., is achieved.

(3) For each water quality task in the work program, the Department of Community Affairs shall request appropriate federal, state, regional, and local agencies to contribute any relevant data, analysis and recommendations, and to take an active role in assisting the County in completing the task. Each agency shall prepare a section to be included in the Department’s report which indicates the agency’s actions relative to the work program. The Department of Community Affairs shall specifically request that the Florida Keys National Marine Sanctuary Water Quality Protection Program Steering Committee (Water Quality Steering Committee) take an active role in coordinating relevant local, state and federal agencies to allocate funding or provide staff to monitor nearshore waters, as necessary, for nutrient reductions.

Rulemaking Authority 380.0552(9), 380.05(22) FS. Law Implemented 380.0552 FS. History–New_________.

 

28-20.140 Comprehensive Plan.

(1) The Monroe County Comprehensive Plan Policy Document, as the same exists on January 1, 2011, is hereby amended to read as follows:

(2) Policy 101.2.13 Monroe County Work Program Conditions and Objectives.

(a) Monroe County shall establish and maintain a Permit Allocation System for new residential development. The Permit Allocation System shall supersede Policy 101.2.1.

(b) The number of permits issued annually for residential development under the Rate of Growth Ordinance shall not exceed a total annual unit cap of 197, plus any available unused ROGO allocations from a previous ROGO year. Each year’s ROGO allocation of 197 units shall be split with a minimum of 71 units allocated for affordable housing in perpetuity and market rate allocations not to exceed 126 residential units per year. Unused ROGO allocations may be retained and made available only for affordable housing and Administrative Relief from ROGO year to ROGO year. Unused allocations for market rate shall be available for Administrative Relief. Any unused affordable allocations will roll over to affordable housing. A ROGO year means the twelve-month period beginning on July 13.

(c) This allocation represents the total number of allocations for development that may be issued during a ROGO year. No exemptions or increases in the number of allocations may be allowed, other than that which may be expressly provided for in the comprehensive plan or for which there is an existing agreement as of September 27 2005, for affordable housing between the Department and the local government in the critical areas.

(d) Allocations and permits to construct a new development or redevelopment that requires a modification or a repair to the onsite sewage treatment and disposal system, per Section 381.0065(4), F.S. and subsection 64E-6.001(4), F.A.C., shall not be issued unless the unit is connected to or will be connected to a central sewer system that has committed funding, a construction permit from the Department of Environmental Protection and the collection system is physically under construction or the unit has an onsite sewage treatment and disposal system that meets the treatment and disposal requirements of Section 381.0065(4), F.S.

(e) Through the Permit Allocation Systems, Monroe County shall direct new growth and redevelopment to areas served by a central sewer system that has committed funding, a construction permit from the Department of Environmental Protection and is physically under construction. Prior to the ranking and approval of awards for an allocation authorizing development of new principal structures, Monroe County, shall coordinate with the central wastewater facility provider and shall increase an applicant’s score by four points for parcels served by a collection line within a central wastewater facility service area where a central wastewater treatment facility has been constructed that meets the treatment standards of Section 403.086(10), F.S., and where treatment capacity is available. The points shall only be awarded if a design permit has been issued for the collection system and the parcel lies within the service area of the wastewater treatment facility.

(f) Beginning November 30, 2011, Monroe County and the Department of Community Affairs shall annually report to the Administration Commission documenting the degree to which the work program objectives for the work program year have been achieved. The Commission shall consider the findings and recommendations provided in those reports and shall determine whether progress has been achieved. If the Commission determines that progress has not been made, the unit cap for residential development shall be reduced by at least 20 percent for the following ROGO year.

(g) If the Commission determines that progress has been made for the work program year, then the Commission may restore the unit cap for residential development for the following year up to a maximum of 197 allocations per ROGO year.

(h) Notwithstanding any other date set forth in this plan, the dates set forth in the work program shall control where conflicts exist.

(i) Wastewater treatment and disposal in Monroe County is governed by the requirements of Section 381.0065(4) and 403.086(10), F.S. Nothing in this rule shall be construed to limit the authority of the Department of Environmental Protection or the Department of Health to enforce Sections 381.0065(4) and 403.086(10), F.S.

(3) Policy 216.1.19. Hurricane Modeling.

For the purposes of hurricane evacuation clearance time modeling purposes, clearance time shall begin when the Monroe County Emergency Management Coordinator issues the evacuation order for permanent residents to evacuate during a Category C-E event. The termination point shall be U.S. Highway One and the Florida Turnpike in Homestead/Florida City.

(4) WORK PROGRAM. Local government annual tasks to achieve progress are the remaining tasks of the Work Program that originate from Rule 28-20.110, F.A.C. Hurricane Evacuation tasks from Year 8, Task Q of the Work Program in Rules 28-20.110 and 28-20.140, F.A.C. Carrying Capacity & Habitat Protection tasks from Year 6, Task C; and Year 8, Task F of the Work Program in Rule 28-20.110, F.A.C. Wastewater tasks from Year 4, Task A; Year 6, Task A; Year 7, Task A; Year 9 Tasks A and B; and Year 10, Tasks A, B, C, D, and E of the Work Program in Rule 28-20.110, F.A.C. Water Quality tasks from Year 8, Task M of the Work Program in Rule 28-20.110, F.A.C.

(a) Carrying Capacity Study Implementation.

1. By July 1, 2011, Monroe County shall adopt the conservation planning mapping (the Tier Zoning Overlay Maps and System) into the Comprehensive Plan based upon the recommendations of the Tier Designation Review Committee with the adjusted Tier boundaries, into the Comprehensive Plan.

2. By July 1, 2011, Monroe County shall adjust the Tier I and Tier IIIA (SPA) boundaries to more accurately reflect the criteria for that Tier as amended by Final Order DCA07-GM166 and implement the Florida Keys Carrying Capacity Study, utilizing the updated habitat data, and based upon the recommendations of the Tier Designation Review Committee Work Group.

3. By July 1, 2011, Monroe County shall create Goal 106 to complete the 10 Year Work Program found in Rule 28-20.110, F.A.C., and to establish objectives to develop a build-out horizon in the Florida Keys and adopt conservation planning mapping into the Comprehensive Plan.

4. By July 1, 2011, Monroe County shall create Objective 106.2 to adopt conservation planning mapping (Tier Maps) into the Monroe Comprehensive Plan based upon the recommendations of the Tier Designation Review Committee. Work Group.

5. By July 1, 2011, Monroe County shall adopt Policy 106.2.1 to require the preparation of updated habitat data and establish a regular schedule for continued update to coincide with evaluation and appraisal report timelines.

6. By July 1, 2011, Monroe County shall adopt Policy 106.2.2 to establish the Tier Designation Work Group Review Committee to consist of representatives selected by the Florida Department of Community Affairs from Monroe County, Florida Fish & Wildlife Conservation Commission, United States Fish & Wildlife Service, Department of Environmental Protection and environmental and other relevant interests. This Committee shall be tasked with the responsibility of Tier designation review utilizing the criteria for Tier placement and best available data to recommend amendments to ensure implementation of and adherence to the Florida Keys Carrying Capacity Study. These proposed amendments shall be recommended during 2009 and subsequently coincide with the Evaluation and Appraisal report timelines beginning with the second Evaluation and Appraisal review which follows the adoption of the revised Tier System and Maps as required above adopted in 2011. Each evaluation and appraisal report submitted following the 2011 evaluation and appraisal report shall also include an analysis and recommendations based upon the process described above.

7. By July 1, 2011 and each July thereafter, Monroe County and the Monroe County Land Authority shall submit a report annually to the Administration Commission on the land acquisition funding and efforts in the Florida Keys to purchase Tier I and Big Pine Key Tier II lands and the purchase of parcels where a Monroe County building permit allocation has been denied for four (4) years or more. The report shall include an identification of all sources of funds and assessment of fund balances within those sources available to the County and the Monroe County Land Authority.

8. By July 1, 2011, Monroe County shall adopt Land Development Regulations to require that administrative relief in the form of the issuance of a building permit is not allowed for lands within the Florida Forever targeted acquisition areas or Tier I lands unless, after 60 days from the receipt of a complete application for administrative relief, it has been determined the parcel will not be purchased by any county, state or federal or any private entity. The County shall develop a mechanism to routinely notify the Department of Environmental Protection of upcoming administrative relief requests at least 6 months prior to the deadline for administrative relief.

9. By July 1, 2011, in order to implement the Florida Keys Carrying Capacity Study, Monroe County shall adopt a Comprehensive Plan Policy to discourage private applications for future land use changes which increase allowable density/intensity.

10. By July 1, 2011, Monroe County shall evaluate its land acquisition needs and state and federal funding opportunities and apply annually to at least one state or federal land acquisition grant program.

11. By July 1, 2011, Monroe County shall enter into a memorandum of understanding with the Department of Community Affairs, Division of Emergency Management, Marathon, Islamorada, Key West, Key Colony Beach, and Layton after a notice and comment period of at least 30 days for interested parties. The memorandum of understanding shall stipulate, based on professionally acceptable data and analysis, the input variables and assumptions, including regional considerations, for utilizing the Florida Keys Hurricane Evacuation Model or other models acceptable to the Department to accurately depict evacuation clearance times for the population of the Florida Keys.

12. By July 1, 2011, the Florida Keys Hurricane Evacuation Model shall be run with the agreed upon variables from the memorandum of understanding to complete an analysis of maximum build-out capacity for the Florida Keys Area of Critical State Concern, consistent with the requirement to maintain a 24-hour evacuation clearance time and the Florida Keys Carrying Capacity Study constraints. This analysis shall be prepared in coordination with the Department of Community Affairs and each municipality in the Keys.

13. By July 1, 2011, the County and the Department of Community Affairs shall update the data for the Florida Keys Hurricane Evacuation Model as professionally acceptable sources of information are released (such as the Census, American Communities Survey, Bureau of Economic and Business Research, and other studies). The County shall also evaluate and address appropriate adjustments to the hurricane evacuation model within each Evaluation and Appraisal Report.

14. By July 1, 2011, the Department of Community Affairs shall apply the derived clearance time to assess and determine the remaining allocations for the Florida Keys Areas of Critical State Concern. The Department will recommend appropriate revisions to the Administration Commission regarding the allocation rates and distribution of allocations to Monroe County, Marathon, Islamorada, Key West, Layton and Key Colony Beach or identify alternative evacuation strategies that support the 24 hour evacuation clearance time. If necessary, the Department of Community Affairs shall work with each local government to amend the Comprehensive Plans to reflect revised allocation rates and distributions or propose rule making to the Administration Commission.

(b) Wastewater Implementation.

1. By July 1, 2011, Monroe County shall annually evaluate and allocate funding for wastewater implementation. Monroe County shall identify any funding in the annual update to the Capital Improvements Element of the Comprehensive Plan.

2. By July 1, 2011, Monroe County shall provide a final determination of cold spots and unfunded service areas requiring upgrade to meet Section 403.086(10) and 381.0065(4)(l), F.S., wastewater treatment and disposal standards. The determination shall be adopted by resolution and shall include a map delineating the non-service areas.

3. By August 1, 2013, Monroe County shall work with the owners of wastewater facilities and throughout the County and the Department of Health (DOH) and the Department of Environmental Protection (DEP) to fulfill the requirements of Sections 403.086(10) and 381.0065(4)(l), F.S., regarding wastewater treatment and disposal. This will include coordination of actions with DOH and DEP to notify owners regarding systems that will not meet the advanced wastewater treatment standards.

4. By August 1, 2011, Monroe County shall adopt an ordinance establishing the upgrade program with implementation dates, time frames, and enforcement for upgrading on-site systems and package plants.

5. By July 1, 2011, Monroe County shall annually draft a resolution requesting the issuance of $50 million of the $200 million of bonds authorized under Section 215.619, F.S., and an appropriation of sufficient debt service for those bonds, for the construction of wastewater projects within the Florida Keys.

6. By July 1, 2011, Monroe County shall develop a mechanism to provide accurate and timely information and establish annual funding allocations necessary to support the issuance of bonds authorized under Section 215.619, F.S., and to assure the timely completion of work as necessary to fulfill any terms and conditions associated with bonds.

7. By July 1, 2011, Monroe County shall evaluate its wastewater needs and state and federal funding opportunities and apply annually to at least one state or federal grant program for wastewater projects and connections.

8. By July 1, 2011, Monroe County shall develop and implement local funding programs necessary to timely fund wastewater construction and future operation, maintenance and replacement of facilities.

9. By July 1, 2011, Monroe County shall, identify by County resolution the areas of the County that will be served by central sewage facilities (“service areas”) and the areas of the County that will not be served by central sewage facilities (“non-service areas”). The non service areas shall be delineated in the form of a map.

10. By July 1, 2013, the Department of Health, Monroe County, and the County’s wastewater provider shall develop and execute an interlocal agreement for non-service areas and unfunded service areas. The agreement shall address mechanisms for the FKAA or other appropriate entity to provide upgrades and central management of onsite sewage treatment and disposal systems located in non-service areas and unfunded service areas. The Department of Health and the Department of Environmental Protection will provide an report to the Department of Community Affairs no later than July 1, 2013, assessing the magnitude of non-compliance and enforcement mechanisms necessary to ensure upgrades of wastewater treatment facilities in accordance with Sections 403.086(10) and 381.0065(4), F.S.

11. By July 1, 2013, and each July thereafter the County shall provide a report of addresses and the property appraiser’s parcel numbers of any property owner that fails or refuses to connect to the central sewer facility within the required timeframe to the Monroe County Health Department, Department of Environmental Protection, and the Department of Community Affairs. This report shall describe the status of enforcement action and provide the circumstances of why enforcement may or may not have been initiated. The Monroe County Department of Health and Department of Community Affairs may proceed with enforcement as necessary and appropriate.

(c) Wastewater Project Implementation.

1. Key Largo Wastewater Treatment Facility. Key Largo Wastewater Treatment District is responsible for wastewater treatment in its service area and the completion of the Key Largo Wastewater Treatment Facility.

a. By July 1, 2011, Monroe County shall complete construction of the South Transmission Line; and

b. By July 1, 2011, Monroe County shall complete design of Collection basin C, E, F, G, H, I, J, and K; and

c. By July 1, 2011, Monroe County shall complete construction of Collection basins E-H; and

d. By July 1, 2011, Monroe County shall schedule construction of Collection basins I-K; and

e. By July 1, 2011, Monroe County shall complete construction of Collection basins I-K; and

f. By July 1, 2011, Monroe County shall complete 50% of hook-ups to Key Largo Regional WWTP; and

g. By July 1, 2012, Monroe County shall complete 75% of hook-ups to Key Largo Regional WWTP; and

h. By July 1, 2013, Monroe County shall complete all remaining connections to Key Largo Regional WWTP.

2. Hawk’s Cay, Duck Key and Conch Key Wastewater Treatment Facility.

a. By July 1, 2011, Monroe County shall complete construction of Hawk’s Cay WWTP upgrade/expansion, transmission, and collection system; and

b. By July 1, 2011, Monroe County shall complete construction of Duck Key collection system; and

c. By July 1, 2011, Monroe County shall initiate property connections to Hawk’s Cay WWTP; and

d. By July 1, 2012, Monroe County shall complete 50% of hook-ups to Hawk’s Cay WWTP; and

e. By July 1, 2013, Monroe County shall complete 75% of hook-ups to Hawk’s Cay WWTP; and

f. By July 1, 2014, Monroe County shall complete all remaining connections to Hawk’s Cay WWTP.

3. South Lower Keys Wastewater Treatment Facility (Big Coppitt Regional System).

a. By July 1, 2012, Monroe County shall complete 75% hookups to South Lower Keys WWTP; and

b. By July 1, 2013, Monroe County shall complete all remaining connections to the South Lower Keys WWTP.

4. Cudjoe Regional Wastewater Treatment Facility.

a. By July 1, 2011, Monroe County shall complete planning and design documents for the Cudjoe Regional Wastewater Treatment Facility for Phases 1 and 2 (WWTP; transmission main and collection system); and

b. By July 1, 2012, Monroe County shall complete construction of Wastewater Treatment Plant Phase 1 and collection systems (Phase 1 is the initial WWTP construction to treat flows from a central collection area); and

c. By July 1, 2012 Monroe County shall initiate construction of Wastewater Treatment Plant Phase 2 (Phase 2 is the planned WWTP expansion to provide additional capacity to treat flows from the expanded collection area); and

d. By July 1, 2013 Monroe County shall complete construction of Wastewater Treatment Plant Phase 2 Expansion; and

e. By July 1, 2013, Monroe County shall complete construction of central collection lines and transmission main; and

f. By July 1, 2013, Monroe County shall initiate property connections – complete 25% of hook-ups to Cudjoe Regional WWTP; and

g. By July 1, 2012, Monroe County shall complete 50% of hook-ups to Cudjoe Regional WWTP; and

h. By July 1, 2014, Monroe County shall complete 75% of hook-ups to Cudjoe Regional WWTP; and

i. By January 1, 2015, Monroe County shall complete all remaining connections to Cudjoe Regional WWTP.

(d) Stormwater Treatment Facilities.

1. By July 1, 2011, Monroe County shall evaluate and allocate funding for stormwater implementation. Monroe County shall identify any funding in the annual update to the Capital Improvements Element of the Comprehensive Plan.

2. By July 1, 2011, Monroe County shall apply for stormwater grants from the South Florida Water Management District.

3. By July 1, 2011, Monroe County shall design and construct Mile Marker 17-19 stormwater runoff management improvements along U.S. Highway One through Joint Participation Agreement with FDOT.

4. By July 1, 2011, Monroe County shall complete Card Sound Road stormwater improvements.

Rulemaking Authority 380.0552(9), 380.05(22) FS. Law Implemented 380.0552 FS. History–New________.


NAME OF PERSON ORIGINATING PROPOSED RULE: Jerry McDaniel, Secretary, Administration Commission
NAME OF AGENCY HEAD WHO APPROVED THE PROPOSED RULE: Administration Commission
DATE PROPOSED RULE APPROVED BY AGENCY HEAD: December 7, 2010
DATE NOTICE OF PROPOSED RULE DEVELOPMENT PUBLISHED IN FAW: November 26, 2008 and February 6, 2009