Rule: 62-330.458 Prev Up Next
Rule Title: General Permit for the Construction and Maintenance of Electric Power Lines by Electric Utilities | |||
Department: | DEPARTMENT OF ENVIRONMENTAL PROTECTION |
Add to MyFLRules Favorites |
|
Division: | Departmental | ||
Chapter: | ENVIRONMENTAL RESOURCE PERMITTING |
Latest version of the final adopted rule presented in Florida Administrative Code (FAC):
Effective Date: | 10/1/2013 | |
History Notes: | Rulemaking Authority 373.026(7), 373.043, 373.118(1), 373.406(5), 373.4131, 373.414(9), 373.418, 403.805(1) FS. Law Implemented 373.118(1), 373.406(5), 373.413, 373.4131, 373.414(9), 373.416, 373.418, 373.426, 403.814(1), 403.814(6), 403.814(7) FS. History–New 10-3-95, Formerly 62-341.620, Amended 10-1-13. | |
References in this version: | No reference(s). |
Notice / Adopted |
Description | ID | Publish Date |
|
---|---|---|---|---|
General Permit for the Construction and Maintenance of Electric Power Lines by Electric Utilities | 13559259 |
Effective: 10/01/2013 |
||
General Permit for the Construction and Maintenance of Electric Power Lines by Electric Utilities | 11610917 |
Effective: 10/03/1995 |