Rule Title: Nuclear or Integrated Gasification Combined Cycle Power Plant Cost Recovery
Department: PUBLIC SERVICE COMMISSION    Add to MyFLRules Favorites
Add to MyFLRules Favorites
Division: Departmental
Chapter: ELECTRIC SERVICE BY ELECTRIC PUBLIC UTILITIES

Latest version of the final adopted rule presented in Florida Administrative Code (FAC):

VIEW_RULE Effective Date: 1/29/2014
History Notes: Rulemaking Authority 350.127(2), 366.05(1), 366.93(2) FS. Law Implemented 366.93 FS. History–New 4-8-07, Amended 2-3-08, 1-29-14.
References in this version: Ref-03577 10 C.F.R. Sec. 73.21(2013)
Ref-03632 42 U.S.C. Sec. 2167(2012)
History of this Rule since Jan. 6, 2006
Notice /
Adopted
Section Description ID Publish
Date
View Text Variances
25-6.0423
waiver from Rule 25-6.0423(6)(c)5, Florida Administrative Code. The rule requires that a utility seeking alternative cost recovery of costs incurred in the siting, design, licensing, and construction of nuclear or integrated .... 17481357 5/2/2016
Vol. 42/85
View Text Final
25-6.0423
Nuclear or Integrated Gasification Combined Cycle Power Plant Cost Recovery 14056869 Effective:
01/29/2014
View Text Proposed
25-6.0423
The rule amendments will implement changes to Section 366.93, FS, enacted by the 2013 Legislature Docket No. 130222-EI 13898953 12/4/2013
Vol. 39/234
View Text Development
25-6.0423
The rule amendments will implement changes to Section 366.93, F.S., enacted by the 2013 Legislature. Docket No. 130222-EI 13446157 8/28/2013
Vol. 39/168
View Text Variances
25-6.0423
Florida Power & Light Company and Progress Energy Florida, Inc., filed on July 31, 2009, in Docket No. 090009-EI, seeking a variance from or partial waiver from subparagraph 25-6.0423(5)(c)4., Florida Administrative Code. .... 7493558 8/14/2009
Vol. 35/32
View Text Variances
25-6.0423
a joint petition from Florida Power & Light Company and Progress Energy Florida, Inc., in Docket No.: 090009-EI, seeking a variance from subparagraph 25-6.0423(5)(c)4., Florida Administrative Code. The rule prescribes the .... 7408392 7/24/2009
Vol. 35/29
View Text Final
25-6.0423
Nuclear or Integrated Gasification Combined Cycle Power Plant Cost Recovery 5171572 Effective:
02/03/2008
View Text Proposed
25-6.0423
The purpose of the rule amendment is to implement Section 366.93, F.S., to promote electric utility investment in Integrated Gasification Combined Cycle (IGCC) power plants by establishing cost recovery mechanisms that allow .... 4915783 12/7/2007
Vol. 33/49
View Text Development
25-6.0423
The purpose of the rule amendment is to implement Section 366.92, F.S., to promote electric utility investment in Integrated Gasification Combined Cycle (IGCC) power plants by establishing cost recovery mechanisms for IGCC .... 4505085 8/31/2007
Vol. 33/35
View Text Final
25-6.0423
Nuclear Power Plant Cost Recovery 3979830 Effective:
04/08/2007
View Text Change
25-6.0423
Nuclear Power Plant Cost Recovery 3811438 2/23/2007
Vol. 33/08
View Text Proposed
25-6.0423
The purpose of the rule is to implement Section 366.93, F.S., to promote electric utility investment in nuclear power plants by establishing cost recovery mechanisms that allow for the recovery in rates of all costs prudently .... 3361649 12/29/2006
Vol. 32/52
View Text Development
25-6.0423
This rule will implement Section 366.93, Florida Statutes, to promote electric utility investment in nuclear power plants by establishing cost recovery mechanisms that allow for the recovery in rates of all costs prudently .... 546418 8/4/2006