Rule: 14-91.007 Prev Up Next
Rule Title: Selection and Award Process | |||
Department: | DEPARTMENT OF TRANSPORTATION |
Add to MyFLRules Favorites |
|
Division: | Departmental | ||
Chapter: | ADMINISTRATION OF COMBINED DESIGN AND CONSTRUCTION CONTRACTS (DESIGN-BUILD) |
Latest version of the final adopted rule presented in Florida Administrative Code (FAC):
Effective Date: | 3/24/2015 | |
History Notes: | Rulemaking Authority 334.044(2), 337.11(7)(b) FS. Law Implemented 337.025, 337.11 FS. History–New 3-13-88, Amended 6-13-90, 2-20-96, 9-3-96, 10-18-00, 5-3-09, 2-17-10, 3-24-15. | |
References in this version: |
Ref-04766 Bridge Qualification Form |
Notice / Adopted |
Description | ID | Publish Date |
|
---|---|---|---|---|
Selection and Award Process | 15764263 |
Effective: 03/24/2015 |
||
To receive public comments and discuss proposed changes to Rule Chapter 14-91, Florida Administrative Code, Administration of Combined Design .... Thursday, December 18, 2014, 1:00 p.m. Florida Department of Transportation Headquarters, Suwannee .... |
15372674 |
12/11/2014 Vol. 40/239 |
||
Selection and Award Process | 15347066 |
12/4/2014 Vol. 40/234 |
||
The amendments to this rule are being made to clarify language and provide options for competitive bidding on design-build projects. | 15284307 |
11/20/2014 Vol. 40/226 |
||
To receive public comments on proposed changes to Rule Chapter 14-91, Florida Administrative Code, Administration of Combined Design and Construction .... Friday, October 10, 2014, 9:00 a.m. Florida Department of Transportation Headquarters, Auditorium, .... |
15101268 |
9/24/2014 Vol. 40/186 |
||
These rules are being amended to clarify procedures used in soliciting and awarding design-build contracts. | 14154257 |
2/7/2014 Vol. 40/26 |
||
D.A.B. Constructors, Inc. vs. Department of Transportation; Case No.: 13-4786RP; Rule No.: 14-91.002, 14-91.004, 14-91.005, 14-91.007; Dismissed | 14146788 |
2/6/2014 Vol. 40/25 |
||
Definitions, Prequalification Requirements, Public Announcement Procedures, Selection and Award Process | 14095669 |
1/23/2014 Vol. 40/15 |
||
D.A.B. Constructors, Inc. vs. Department of Transportation; Case No.: 13-4786RP; Rule No.: 14-91.002, 14-91.004, 14-91.005, 14-91.007; Petition | 14018748 |
1/7/2014 Vol. 40/04 |
||
The amendments to this rule are being made to clarify language and provide options for competitive bidding on design-build projects. | 13856370 |
11/22/2013 Vol. 39/228 |
||
These rules are being amended or repealed to clarify procedures used in soliciting and awarding design-build contracts. | 12621366 |
2/7/2013 Vol. 39/26 |
||
Selection and Award Process | 8255008 |
Effective: 02/17/2010 |
||
Selection and Award Process | 8054994 |
12/24/2009 Vol. 35/51 |
||
Selection and Award Process | 7693766 |
10/2/2009 Vol. 35/39 |
||
A new subsection (9) is added to Rule 14-91.007, F.A.C., to clarify the compensation of short-listed design-build firms. | 7509660 |
8/21/2009 Vol. 35/33 |
||
A new subsection (9) is added to Rule 14-91.007, F.A.C., to clarify the compensation of short-listed design-build firms. | 7260176 |
6/19/2009 Vol. 35/24 |
||
Selection and Award Process | 7066176 |
Effective: 05/03/2009 |
||
This is an amendment to subsection 14-91.007(5), F.A.C., to revise the composition of the Design-Build Technical Review Committees. | 6875183 |
3/13/2009 Vol. 35/10 |
||
This is an amendment to subsection 14-91.007(5), F.A.C., to revise the composition of the Design-Build Technical Review Committees. | 6575841 |
12/31/2008 Vol. 34/53 |
||
Selection and Award Process | 6362732 |
10/31/2008 Vol. 34/44 |
||
A new subsection (9) is added to Rule 14-91.007, F.A.C., to clarify the compensation of short-listed design-build firms. | 4729252 |
10/19/2007 Vol. 33/42 |
||
A new subsection (9) is added to Rule 14-91.007, F.A.C., to clarify the compensation of design-build firms. | 4672216 |
10/5/2007 Vol. 33/40 |
||
Selection and Award Process | 1337647 |
Effective: 10/18/2000 |