Rule: 62-672.760 Prev Up Next
| Rule Title: Procedures for Decanting Process Water from Top of Phosphogypsum Stack | |||
| Department: | DEPARTMENT OF ENVIRONMENTAL PROTECTION |
![]() Add to MyFLRules Favorites |
|
| Division: | Departmental | ||
| Chapter: | MINIMUM REQUIREMENTS FOR EARTHEN DAMS USED IN PHOSPHATE MINING AND BENEFICIATION OPERATIONS AND FOR DIKES USED IN PHOSPHOGYPSUM STACK SYSTEM IMPOUNDMENTS | ||
Latest version of the final adopted rule presented in Florida Administrative Code (FAC):
|
Effective Date: | 6/28/1999 |
| History Notes: | Rulemaking Authority 403.4155 FS. Law Implemented 403.4155 FS. History–New 6-28-99. | |
| References in this version: | No reference(s). |
| Notice / Adopted |
Description | ID | Publish Date |
|
|---|---|---|---|---|
|
Procedures for Decanting Process Water from Top of Phosphogypsum Stack | 2294843 |
Effective: 06/28/1999 |
|