Rule: 25-6.065 Prev Up Next
Rule Title: Interconnection and Metering of Customer-Owned Renewable Generation | |||
Department: | PUBLIC SERVICE COMMISSION |
Add to MyFLRules Favorites |
|
Division: | Departmental | ||
Chapter: | ELECTRIC SERVICE BY ELECTRIC PUBLIC UTILITIES |
Latest version of the final adopted rule presented in Florida Administrative Code (FAC):
Effective Date: | 4/7/2008 | |
History Notes: | Rulemaking Authority 350.127(2), 366.05(1), 366.91(5), 366.92(5) FS. Law Implemented 366.02(2), 366.04(2)(c), (5), (6), 366.041, 366.05(1), 366.81, 366.82(1), (2), 366.91, 366.92 FS. History–New 2-11-02, Amended 4-7-08. | |
References in this version: | No reference(s). |
Notice / Adopted |
Description | ID | Publish Date |
|
---|---|---|---|---|
EcoSmart Solution, LLC The petition asks the Florida Public Service Commission to declare that (1) the geothermal and solar photovoltaic system that EcoSmart .... |
25447967 |
1/12/2022 Vol. 48/08 |
||
IGS Solar, LLC The Florida Public Service Commission issued a declaratory statement that: (1) IGS Solar’s proposed residential solar equipment lease, .... |
21775547 |
4/24/2019 Vol. 45/80 |
||
IGS Solar, LLC, on February 8, 2019 .... |
21505790 |
2/11/2019 Vol. 45/28 |
||
from Tesla Inc., on December 3, 2018. that Tesla Inc.’s leasing of solar electric equipment to residential lessees, pursuant to Tesla’s standard form SolarLease, does .... |
21225557 |
12/5/2018 Vol. 44/235 |
||
Vivint Solar Developer, LLC, on May 23, 2018. The petition asks the Florida Public Service Commission to declare pursuant to Section 366.02, F.S., Rule 25-6.065, F.A.C., Order .... |
20468278 |
5/30/2018 Vol. 44/105 |
||
Sunrun Inc. The Florida Public Service Commission issued a declaratory statement that: (1) Sunrun’s residential solar equipment lease as described .... |
20437529 |
5/21/2018 Vol. 44/99 |
||
Sunrun, Inc., on December 29, 2017. The petition asks the Florida Public Service Commission to declare pursuant to Section 366.02, F.S., Rule 25-6.065, F.A.C., and Order .... |
19918191 |
1/4/2018 Vol. 44/03 |
||
permenant waiver from Rule 25-6.065)6)(a), Florida Administrative Code. | 13744626 |
10/30/2013 Vol. 39/212 |
||
waiver from paragraphs 25-6.065(5)(d) and (e), Florida Administrative Code, Docket No.: 120012-EI, Petition for variance and waiver of certain contractual requirements in Rule 25-6.065, F.A.C., by Progress Energy Florida, .... | 10927164 |
1/20/2012 Vol. 38/03 |
||
Interconnection and Metering of Customer-Owned Renewable Generation | 5455200 |
Effective: 04/07/2008 |
||
The purpose of the rule amendments is to promote the development of customer-owned renewable generation. This will offset electric consumption and help diversify the types of fuel used to generate electricity in Florida, .... | 5049449 |
1/4/2008 Vol. 34/01 |
||
The Florida Public Service Commission is seeking public input and discussion addressing issues associated with expedited interconnection with .... October 15, 2007 - 9:30 a.m. - 5:00 p.m. Betty Easley Conference Center, Room 148, 4075 Esplanade Way, .... |
4645735 |
9/28/2007 Vol. 33/39 |
||
To amend Rule 25-6.065, F.A.C., to encourage further development of renewable resources within the state and to develop Rules 25-6.066 and 25-6.067, F.A.C., on net-metering and expedited interconnection standards for customer-owned .... | 4431559 |
8/10/2007 Vol. 33/32 |
||
Interconnection of Small Photovoltaic Systems | 1461322 |
Effective: 02/11/2002 |